The 3 t/h sodium sulfate decahydrate project in Kazakhstan, designed by our company, officially commenced construction in mid-May. Adopting mirabilite as the raw material, the production process consists of melting, purification, evaporative crystallization, drying and packaging to meet the production targets. The full design covers process flow, equipment installations, electrical instruments, automatic control systems, buildings and structures, plant transportation, safety & fire protection, as well as water supply and drainage systems.
Customs clearance and cross-border transportation of all equipment have been underway since the start of the year. Our professional technical personnel arrived at the site in mid-May to guide installation and construction. The scheduled construction period is approximately two and a half months. Later, our team will conduct commissioning and operational guidance to ensure the production line reaches all designed performance indicators on schedule, delivering both economic and social benefits for the company.